Back to projects

Kenmount Rd. Storm Sewer Replacement

St. John's, Newfoundland and Labrador

completeWastewaterNRP
Federal contribution
$2.5M
$2,546,026
Federal share33%

of $7.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 19, 2016
2017201920212023
Built

Approved 4 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Ultimate recipient
City of St. John's
Construction start
Jun 18, 2018(actual)
Construction end
Oct 31, 2022(actual)

Against the original forecast

  • Construction start3 months lateforecast Apr 1, 2018
  • Construction end4 weeks earlyforecast Nov 30, 2022

Also in St. John's