Portugal Cove Road Water Transmission Main Replacement Project - Phase 2 (New Cove Road to First Avenue)
St. John's, Newfoundland and Labrador
Federal contribution
$2.7M
$2,652,573
Federal share33%
of $8.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 19, 2017
20182019
Built
Approved 7 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- City of St. John's
- Construction start
- Oct 23, 2017(actual)
- Construction end
- Jan 18, 2019(actual)
Against the original forecast
- Construction start6 months lateforecast May 1, 2017
- Construction end8 months earlyforecast Sep 30, 2019