Road Improvements - Harbour View Road and Burnt Head Road
Lushes Bight-Beaumont-Beaumont North, Newfoundland and Labrador
Federal contribution
$102,972
Federal share33%
of $314.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 16, 2016
201720182019202020212022
Built
Approved 4 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Lushes Bight-Beaumont-Beaumont North
- Construction start
- Jul 18, 2017(actual)
- Construction end
- Aug 11, 2022(actual)
Against the original forecast
- Construction start5 weeks earlyforecast Aug 21, 2017
- Construction end10 months earlyforecast May 30, 2023
Also in Lushes Bight-Beaumont-Beaumont North
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46741 in the federal list. How to read these figures.