Back to projects

Burnt Heat Road Paving

Lushes Bight-Beaumont-Beaumont North, Newfoundland and Labrador

completeHighways and RoadsRNIS
Federal contribution
$65,930
Federal share33%

of $197.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 14, 2020
20212022
Built

Approved 5 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Jul 27, 2021(actual)
Construction end
Nov 2, 2022(actual)

Against the original forecast

  • Construction start3 months lateforecast May 1, 2021
  • Construction end5 months lateforecast May 31, 2022

Also in Lushes Bight-Beaumont-Beaumont North

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56758 in the federal list. How to read these figures.