Paving - Hillview, Webcon Road, Frenchman's Cove Point, Shady Lane and John Franks Road

Humber Arm South, Newfoundland and Labrador

completeHighways and RoadsSCF
Federal contribution
$97,037
Federal share33%

of $291.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 16, 2016
20172018
Built

Approved 4 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Humber Arm South
Construction start
Jun 19, 2018(actual)
Construction end
Sep 20, 2018(actual)

Against the original forecast

  • Construction start5 weeks lateforecast May 15, 2018
  • Construction end5 weeks lateforecast Aug 15, 2018