Paving - Hillview, Webcon Road, Frenchman's Cove Point, Shady Lane and John Franks Road
Humber Arm South, Newfoundland and Labrador
Federal contribution
$97,037
Federal share33%
of $291.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 16, 2016
20172018
Built
Approved 4 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Humber Arm South
- Construction start
- Jun 19, 2018(actual)
- Construction end
- Sep 20, 2018(actual)
Against the original forecast
- Construction start5 weeks lateforecast May 15, 2018
- Construction end5 weeks lateforecast Aug 15, 2018