First Avenue New Storm System Upgrades

Humber Arm South, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$206,799
Federal share40%

of $517.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 16, 2020
2021
Built

Approved 6 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Humber Arm South
Construction start
Oct 5, 2021(actual)
Construction end
Nov 8, 2021(actual)

Against the original forecast

  • Construction start3 months lateforecast Jul 1, 2021
  • Construction end5 months earlyforecast Mar 31, 2022

Also in Humber Arm South

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56899 in the federal list. How to read these figures.