Highway 11/17 - 4 Lane Expansion, CPR Overhead at Ouimet to Dorion East Loop

Dorion, Ontario

completeHighways and RoadsMIC
Federal contribution
$37.4M
$37,431,500
Federal share50%

of $74.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 30, 2019
2017201920212023
Built

Approved 2.7 years before the announcement.

Program
Building Canada Fund - Major Infrastructure Component
Construction start
Nov 1, 2020(actual)
Construction end
Oct 31, 2023(actual)

Against the original forecast

  • Construction start6 months lateforecast May 4, 2020
  • Construction end12 months lateforecast Nov 4, 2022

Also in Dorion

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46765 in the federal list. How to read these figures.