Highway 11/17 - 4 Lane Expansion, CPR Overhead at Ouimet to Dorion East Loop
Federal contribution
$37.4M
$37,431,500
Federal share50%
of $74.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 30, 2019
2017201920212023
Built
Approved 2.7 years before the announcement.
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- Ontario Ministry of Transportation
- Construction start
- Nov 1, 2020(actual)
- Construction end
- Oct 31, 2023(actual)
Against the original forecast
- Construction start6 months lateforecast May 4, 2020
- Construction end12 months lateforecast Nov 4, 2022
Also in Dorion
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46765 in the federal list. How to read these figures.