Reconstruction of open roadside ditches and culvert replacements on the Fish Hatchery Road

Dorion, Ontario

completeWastewaterCWWF
Federal contribution
$49,825
Federal share50%

of $99.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 17, 2017
201820192020
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Township of Dorion
Construction start
Aug 3, 2017(actual)
Construction end
Sep 15, 2020(actual)

Against the original forecast

  • Construction start3 months lateforecast May 1, 2017
  • Construction end7 weeks earlyforecast Oct 31, 2020