Reconstruction of open roadside ditches and culvert replacements on the Fish Hatchery Road
Federal contribution
$49,825
Federal share50%
of $99.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 17, 2017
201820192020
Built
Approved 6 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Dorion
- Construction start
- Aug 3, 2017(actual)
- Construction end
- Sep 15, 2020(actual)
Against the original forecast
- Construction start3 months lateforecast May 1, 2017
- Construction end7 weeks earlyforecast Oct 31, 2020
Also in Dorion
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50239 in the federal list. How to read these figures.