Harden St bridge rehabilitation

Cobourg, Ontario

completeHighways and RoadsSCF
Federal contribution
$108,086
Federal share33%

of $324.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 7, 2016
2017
Built

Approved 7 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Cobourg
Construction start
May 17, 2017(actual)
Construction end
Jul 28, 2017(actual)

Against the original forecast

  • Construction start2 weeks lateforecast May 1, 2017