Eagle Lake Watermain Upgrade

Kenora District, Ontario

completeDrinking WaterSCF
Federal contribution
$583,447
Federal share32%

of $1.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 7, 2016
20172018
Built

Approved 7 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Eagle Lake First Nation
Construction start
Aug 7, 2018(actual)
Construction end
Oct 20, 2018(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Jun 11, 2018
  • Construction end4 weeks earlyforecast Nov 19, 2018