Water Treatment Plant Upgrade
Federal contribution
$500,000
Federal share33%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 7, 2016
2017201820192020
Built
Approved 7 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Grassy Narrows First Nation
- Construction start
- May 29, 2019(actual)
- Construction end
- Sep 21, 2020(actual)
Against the original forecast
- Construction start9 months lateforecast Aug 30, 2018
- Construction end6 weeks earlyforecast Nov 1, 2020
Also in Kenora District
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46844 in the federal list. How to read these figures.