Marmora Sewage Forcemain Replacement
Federal contribution
$236,538
Federal share33%
of $709.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 7, 2016
2017
Built
Approved 7 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Municipality of Marmora and Lake
- Construction start
- Jul 5, 2017(actual)
- Construction end
- Sep 30, 2017(actual)
Against the original forecast
- Construction start15 months lateforecast Apr 1, 2016
- Construction end6 months earlyforecast Mar 31, 2018
Also in Marmora and Lake
- Highway 7 Watermain Upgrades$382.8K
- Marmora Watermain and Sanitary Sewer Extension$271.4K
- Booster Park Office Expansion$80.0K
- Sewer Collection System Rehabilitation Addressing High Infiltration Rates$33.6K
- Wastewater Treatment Plant refurbishment of clarifier overflow baffles, restoration of concrete, and installation of new clarifier drive mechanism$33.6K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46860 in the federal list. How to read these figures.