Back to projects

Sewer Collection System Rehabilitation Addressing High Infiltration Rates

Marmora and Lake, Ontario

completeWastewaterCWWF
Federal contribution
$33,579
Federal share50%

of $67.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
20182019
Built
Program
Clean Water and Wastewater Fund
Construction start
Jul 12, 2017(actual)
Construction end
Jan 25, 2019(actual)

Against the original forecast

  • Construction start3 months lateforecast Apr 1, 2017
  • Construction end7 months lateforecast Jun 30, 2018

Also in Marmora and Lake