Disaster Mitigation of the Wastewater Treatment Plant (WWTP)

North Perth, Ontario

completeWastewaterSCF
Federal contribution
$1.6M
$1,628,078
Federal share25%

of $6.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 7, 2016
20172018201920202021
Built

Approved 7 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Municipality of North Perth
Construction start
Nov 15, 2017(actual)
Construction end
Dec 31, 2020(actual)

Against the original forecast

  • Construction start3 months lateforecast Aug 14, 2017
  • Construction end17 months lateforecast Jul 26, 2019