Disaster Mitigation of the Wastewater Treatment Plant (WWTP)
Federal contribution
$1.6M
$1,628,078
Federal share25%
of $6.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 7, 2016
20172018201920202021
Built
Approved 7 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Municipality of North Perth
- Construction start
- Nov 15, 2017(actual)
- Construction end
- Dec 31, 2020(actual)
Against the original forecast
- Construction start3 months lateforecast Aug 14, 2017
- Construction end17 months lateforecast Jul 26, 2019