Rehabilitation of Biosolids Aerobic Digester
Federal contribution
$426,102
Federal share9%
of $4.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 26, 2017
20182019
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of North Perth
- Construction start
- Dec 14, 2017(actual)
- Construction end
- Jun 24, 2019(actual)
Against the original forecast
- Construction start2 weeks lateforecast Nov 30, 2017
- Construction end3 months lateforecast Mar 31, 2019
Also in North Perth
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48522 in the federal list. How to read these figures.