Back to projects

Rainbow Riders Redevelopment

St. John's, Newfoundland and Labrador

completeRecreationNRP
Federal contribution
$1.4M
$1,422,308
Federal share28%

of $5.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 25, 2016
20172018
Built

Approved 3 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Construction start
Dec 7, 2016(actual)
Construction end
Sep 30, 2018(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Oct 30, 2016
  • Construction end12 months lateforecast Sep 30, 2017

Also in St. John's