Rainbow Riders Redevelopment
St. John's, Newfoundland and Labrador
Federal contribution
$1.4M
$1,422,308
Federal share28%
of $5.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 25, 2016
20172018
Built
Approved 3 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Construction start
- Dec 7, 2016(actual)
- Construction end
- Sep 30, 2018(actual)
Against the original forecast
- Construction start5 weeks lateforecast Oct 30, 2016
- Construction end12 months lateforecast Sep 30, 2017
Also in St. John's
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46890 in the federal list. How to read these figures.