Whitehorse Public Transit Buses
Federal contribution
$785,104
Federal share66%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 22, 2016
20172018
Built
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Whitehorse
- Construction start
- Jan 12, 2018(actual)
- Construction end
- Feb 27, 2018(actual)
Against the original forecast
- Construction start7 months lateforecast Jun 1, 2017
- Construction end13 months earlyforecast Mar 31, 2019
Also in Whitehorse
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46902 in the federal list. How to read these figures.