Back to projects

Rapid Transit Fleet Expansion - Millennium Line

Anmore, British Columbia

completePublic TransitPTIF
Federal contribution
$15.1M
$15,112,930
Federal share50%

of $30.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 16, 2016
201720182019
Built
Program
Public Transit Infrastructure Fund
Ultimate recipient
Metro Vancouver
Construction start
Nov 22, 2016(actual)
Construction end
Sep 3, 2019(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Oct 3, 2016
  • Construction end19 months earlyforecast Mar 31, 2021

Also in Anmore

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46906 in the federal list. How to read these figures.