Rapid Transit Fleet Expansion - Canada Line
Federal contribution
$42.7M
$42,712,933
Federal share50%
of $85.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 16, 2016
2017201820192020
Built
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Metro Vancouver
- Construction start
- Oct 18, 2017(actual)
- Construction end
- Apr 30, 2020(actual)
Against the original forecast
- Construction start3 months lateforecast Aug 1, 2017
- Construction end11 months earlyforecast Mar 31, 2021
Also in Anmore
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46910 in the federal list. How to read these figures.