Tagish pipe firehall to water treatment plant

Carcross/Tagish First Nation, Yukon

completeDrinking WaterCWWF
Federal contribution
$307,500
Federal share75%

of $410.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 22, 2016
201720182019
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Government of Yukon
Construction start
Jul 1, 2016(actual)
Construction end
Jul 13, 2019(actual)

Against the original forecast

  • Construction end3 weeks earlyforecast Jul 31, 2019

Also in Carcross/Tagish First Nation

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46911 in the federal list. How to read these figures.