Nares River Bridge Replacement

Whitehorse, Yukon

completeHighways and RoadsSCF
Federal contribution
$9.6M
$9,573,750
Federal share75%

of $12.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2016
2017201820192020
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
City of Whitehorse
Construction start
Feb 1, 2018(actual)
Construction end
Oct 13, 2020(actual)

Against the original forecast

  • Construction end11 months earlyforecast Aug 31, 2021