Nisutlin Bay Bridge
Federal contribution
$41.3M
$41,250,000
Federal share26%
of $158.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2016
today
2017202020232026
BuiltForecast
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Village of Teslin
- Construction start
- Jun 15, 2022(actual)
- Construction end
- Mar 31, 2028(forecast)
Against the original forecast
- Construction start11 months lateforecast Jul 1, 2021
Also in Teslin