Teslin Fire Hall
Federal contribution
$4.1M
$4,080,311
Federal share74%
of $5.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 6, 2019
2019202020212022
Built
Approved 7 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Village of Teslin
- Construction start
- Jul 15, 2021(actual)
- Construction end
- Aug 11, 2022(actual)
Against the original forecast
- Construction start2 weeks earlyforecast Jul 30, 2021
- Construction end15 months earlyforecast Oct 31, 2023