Expansion Buses

Undefined, British Columbia

completePublic TransitPTIF
Federal contribution
$8.3M
$8,265,212
Federal share50%

of $16.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 19, 2016
201720182019
Built

Approved 5 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
British Columbia Transit
Construction start
Jun 3, 2016(actual)
Construction end
Feb 1, 2019(actual)

Against the original forecast

  • Construction start3 months earlyforecast Sep 8, 2016
  • Construction end14 months earlyforecast Mar 31, 2020

Also in Undefined

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46941 in the federal list. How to read these figures.