Douglas St. Bus Lane (Tolmie-Mckenzie)

Saanich, British Columbia

completePublic TransitPTIF
Federal contribution
$4.6M
$4,625,000
Federal share50%

of $9.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 19, 2016
201720182019
Built

Approved 5 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Mar 7, 2018(actual)
Construction end
Dec 5, 2018(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jan 14, 2018
  • Construction end4 months earlyforecast Mar 31, 2019

Also in Saanich

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46943 in the federal list. How to read these figures.