Back to projects

McKenzie/Colwood Bus-on-Shoulder

Saanich, British Columbia

underwayPublic TransitPTIS
Federal contribution
$28.0M
$28,012,225
Federal share40%

of $70.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 29, 2024
today
2024202520262027
BuiltForecast

Approved 7 months before the announcement.

Program
Public Transit Infrastructure Stream
Construction start
Mar 3, 2025(actual)
Construction end
Oct 31, 2027(forecast)

Against the original forecast

  • Construction start4 weeks lateforecast Feb 3, 2025

Also in Saanich

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67763 in the federal list. How to read these figures.