Yukon River Bridge Rehabilitation
Federal contribution
$3.2M
$3,221,509
Federal share74%
of $4.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2016
2017
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Government of Yukon
- Construction start
- Mar 27, 2017(actual)
- Construction end
- Oct 31, 2017(actual)
Against the original forecast
- Construction end11 months earlyforecast Oct 1, 2018
Also in Carmacks
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46945 in the federal list. How to read these figures.