Carmacks Public Works building, Firehall and Emergency Medical Services (EMS)

Carmacks, Yukon

underwayAdministration, Emergency and Public WorksSCF
Federal contribution
$8.9M
$8,903,846
Federal share75%

of $11.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 4, 2019
today
201920212023202520272029
BuiltForecast

Approved 8 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Village of Carmacks
Construction start
Sep 15, 2021(actual)
Construction end
Aug 31, 2028(forecast)

Against the original forecast

  • Construction start6 weeks lateforecast Aug 1, 2021