Alaska Highway Restoration

Whitehorse, Yukon

completeHighways and RoadsSCF
Federal contribution
$651,112
Federal share75%

of $868.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2016
2017
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
City of Whitehorse
Construction start
Aug 16, 2016(actual)
Construction end
Sep 1, 2017(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Jul 11, 2016
  • Construction end5 weeks lateforecast Jul 31, 2017

Also in Whitehorse

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46949 in the federal list. How to read these figures.