2016 Water Main Insulation, Chlorination System & House Replacement, & Paddy's Pond Dam Replacement
Brent's Cove, Newfoundland and Labrador
Federal contribution
$265,005
Federal share50%
of $531.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2016
2017
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Brent's Cove
- Construction start
- Sep 1, 2017(actual)
- Construction end
- Oct 25, 2017(actual)
Against the original forecast
- Construction start15 months lateforecast Jun 1, 2016
- Construction end3 months lateforecast Jul 31, 2017
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46960 in the federal list. How to read these figures.