Water System Improvements

Rose Blanche-Harbour Le Cou, Newfoundland and Labrador

completeDrinking WaterCWWF
Federal contribution
$183,655
Federal share35%

of $532.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2016
201720182019
Built
Program
Clean Water and Wastewater Fund
Construction start
Feb 4, 2019(actual)
Construction end
Jul 31, 2019(actual)

Against the original forecast

  • Construction start8 weeks earlyforecast Apr 1, 2019
  • Construction end2 months earlyforecast Oct 1, 2019

Also in Rose Blanche-Harbour Le Cou

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46970 in the federal list. How to read these figures.