Water System Upgrades - Plank Lane

Freshwater, Newfoundland and Labrador

completeDrinking WaterCWWF
Federal contribution
$88,947
Federal share47%

of $189.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2016
2017
Built
Program
Clean Water and Wastewater Fund
Construction start
May 31, 2017(actual)
Construction end
Nov 30, 2017(actual)

Against the original forecast

  • Construction end4 months earlyforecast Mar 31, 2018

Also in Freshwater