Drill Artesian Wells
Lodge Bay, Newfoundland and Labrador
Federal contribution
$61,148
Federal share50%
of $122.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2016
201720182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Local Service District of Lodge Bay
- Construction start
- Jun 1, 2019(actual)
- Construction end
- Jul 10, 2019(actual)
Against the original forecast
- Construction start13 months lateforecast May 15, 2018
- Construction end9 months earlyforecast Mar 31, 2020
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46986 in the federal list. How to read these figures.