New Phase - Water and Sewer
Charlottetown (Labrador), Newfoundland and Labrador
Federal contribution
$331,669
Federal share50%
of $669.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2016
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Charlottetown
- Construction start
- Sep 1, 2017(actual)
- Construction end
- Jun 30, 2018(actual)
Against the original forecast
- Construction start2 weeks lateforecast Aug 15, 2017
- Construction end6 months earlyforecast Dec 31, 2018
Also in Charlottetown (Labrador)
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46991 in the federal list. How to read these figures.