Chlorine Booster Station
Howley, Newfoundland and Labrador
Federal contribution
$121,408
Federal share50%
of $245.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2016
201720182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Howley
- Construction start
- Jul 27, 2018(actual)
- Construction end
- Jan 10, 2019(actual)
Against the original forecast
- Construction start3 months lateforecast May 1, 2018
- Construction end3 months earlyforecast Mar 31, 2019
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47036 in the federal list. How to read these figures.