Chlorine Booster Station

Howley, Newfoundland and Labrador

completeDrinking WaterCWWF
Federal contribution
$121,408
Federal share50%

of $245.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2016
201720182019
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Howley
Construction start
Jul 27, 2018(actual)
Construction end
Jan 10, 2019(actual)

Against the original forecast

  • Construction start3 months lateforecast May 1, 2018
  • Construction end3 months earlyforecast Mar 31, 2019

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47036 in the federal list. How to read these figures.