Water System Upgrades

Happy Valley-Goose Bay, Newfoundland and Labrador

completeDrinking WaterCWWF
Federal contribution
$413,970
Federal share50%

of $827.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2016
2017201820192020
Built
Program
Clean Water and Wastewater Fund
Construction start
Oct 18, 2018(actual)
Construction end
Mar 11, 2020(actual)

Against the original forecast

  • Construction start5 months earlyforecast Apr 1, 2019
  • Construction end5 months lateforecast Oct 1, 2019