Water Dam and Distribution

Gallants, Newfoundland and Labrador

completeDrinking WaterCWWF
Federal contribution
$184,994
Federal share50%

of $370.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2016
20172018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Gallants
Construction start
Oct 30, 2017(actual)
Construction end
Nov 23, 2018(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Sep 1, 2017
  • Construction end5 months lateforecast Jun 29, 2018

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47070 in the federal list. How to read these figures.