Water Dam and Distribution
Gallants, Newfoundland and Labrador
Federal contribution
$184,994
Federal share50%
of $370.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2016
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Gallants
- Construction start
- Oct 30, 2017(actual)
- Construction end
- Nov 23, 2018(actual)
Against the original forecast
- Construction start8 weeks lateforecast Sep 1, 2017
- Construction end5 months lateforecast Jun 29, 2018