Waterline Extension to Clam Bank Cove

Lourdes, Newfoundland and Labrador

completeDrinking WaterCWWF
Federal contribution
$275,374
Federal share29%

of $939.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2016
201720182019
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Lourdes
Construction start
May 29, 2017(actual)
Construction end
Jan 31, 2019(actual)

Against the original forecast

  • Construction start4 weeks lateforecast May 1, 2017
  • Construction end9 months earlyforecast Nov 15, 2019