Water System Infrastructure Upgrades

Deep Bight, Newfoundland and Labrador

completeDrinking WaterCWWF
Federal contribution
$353,958
Federal share50%

of $707.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2016
201720182019
Built
Program
Clean Water and Wastewater Fund
Construction start
Oct 2, 2017(actual)
Construction end
Nov 30, 2018(actual)

Against the original forecast

  • Construction start2 months lateforecast Aug 1, 2017
  • Construction end4 weeks earlyforecast Dec 31, 2018

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47080 in the federal list. How to read these figures.