Pressure Booster Station Replacement
Happy Adventure, Newfoundland and Labrador
Federal contribution
$231,909
Federal share50%
of $464.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2016
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Village of Happy Adventure
- Construction start
- Oct 31, 2017(actual)
- Construction end
- Sep 30, 2018(actual)
Against the original forecast
- Construction start2 months lateforecast Sep 1, 2017
- Construction end6 months earlyforecast Mar 31, 2019