Back to projects

Accessibility Improvements on Routes 1, 2, 3 & 5

St. John's, Newfoundland and Labrador

completePublic TransitPTIF
Federal contribution
$405,306
Federal share45%

of $906.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2016
20172018
Built
Program
Public Transit Infrastructure Fund
Ultimate recipient
City of St. John's
Construction start
May 15, 2017(actual)
Construction end
Apr 6, 2018(actual)

Against the original forecast

  • Construction start2 weeks lateforecast May 1, 2017
  • Construction end4 months earlyforecast Jul 31, 2018

Also in St. John's