Filter Cleaning Unit

St. John's, Newfoundland and Labrador

completePublic TransitPTIF
Federal contribution
$45,342
Federal share50%

of $90.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2016
2017
Built
Program
Public Transit Infrastructure Fund
Ultimate recipient
City of St. John's
Construction start
Oct 28, 2016(actual)
Construction end
Feb 20, 2017(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Sep 1, 2016

Also in St. John's

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47103 in the federal list. How to read these figures.