Water Piping and Sewage Collection System - Phase 2

Sandringham, Newfoundland and Labrador

completeWastewaterCWWF
Federal contribution
$390,800
Federal share50%

of $781.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2016
20172018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Sandringham
Construction start
Sep 15, 2017(actual)
Construction end
Jun 30, 2018(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Sep 1, 2017
  • Construction end6 months earlyforecast Dec 31, 2018

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47112 in the federal list. How to read these figures.