Back to projects

Rural Waterline Expansion

Rosedale, Manitoba

completeDrinking WaterCWWF
Federal contribution
$1.4M
$1,358,879
Federal share45%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 25, 2016
20172018
Built
Program
Clean Water and Wastewater Fund
Construction start
Aug 14, 2017(actual)
Construction end
Jan 29, 2018(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jul 17, 2017

Also in Rosedale

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47132 in the federal list. How to read these figures.