Rural Waterline Expansion: Phase 3

North Norfolk, Manitoba

completeDrinking WaterCWWF
Federal contribution
$1.4M
$1,371,633
Federal share46%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 25, 2016
20172018
Built
Program
Clean Water and Wastewater Fund
Construction start
Jul 11, 2017(actual)
Construction end
Jan 19, 2018(actual)

Against the original forecast

  • Construction start6 weeks earlyforecast Aug 21, 2017
  • Construction end5 weeks lateforecast Dec 15, 2017