Rural Waterline Expansion: Phase 3
Federal contribution
$1.4M
$1,371,633
Federal share46%
of $3.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 25, 2016
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Rural Municipality of North Norfolk
- Construction start
- Jul 11, 2017(actual)
- Construction end
- Jan 19, 2018(actual)
Against the original forecast
- Construction start6 weeks earlyforecast Aug 21, 2017
- Construction end5 weeks lateforecast Dec 15, 2017
Also in North Norfolk
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47133 in the federal list. How to read these figures.