Rural Waterline Expansion: Phase 2

Brenda-Waskada, Manitoba

completeDrinking WaterCWWF
Federal contribution
$2.5M
$2,500,000
Federal share50%

of $5.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 25, 2016
20172018
Built
Program
Clean Water and Wastewater Fund
Construction start
May 17, 2017(actual)
Construction end
Feb 9, 2018(actual)

Against the original forecast

  • Construction start2 weeks lateforecast May 1, 2017
  • Construction end3 weeks earlyforecast Feb 28, 2018

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47135 in the federal list. How to read these figures.