Wastewater Treatment Plant
Federal contribution
$947,486
Federal share38%
of $2.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 25, 2016
2017201820192020
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Manitoba Ministry of Indigenous and Northern Relations
- Construction start
- May 7, 2017(actual)
- Construction end
- Mar 31, 2020(actual)
Against the original forecast
- Construction start8 months lateforecast Sep 1, 2016
- Construction end5 months lateforecast Oct 31, 2019
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47136 in the federal list. How to read these figures.