Back to projects

SWPCC Biosolids System Upgrades

Summerside, Prince Edward Island

completeWastewaterCWWF
Federal contribution
$1.0M
$1,027,325
Federal share50%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 3, 2016
201720182019
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Summerside
Construction start
Sep 1, 2017(actual)
Construction end
Mar 31, 2019(actual)

Also in Summerside