Sanitary sewer pumping facility replacement
Federal contribution
$500,000
Federal share50%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 16, 2016
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Regional Municipality of Cape Breton
- Construction start
- Apr 30, 2018(actual)
- Construction end
- Oct 22, 2018(actual)
Against the original forecast
- Construction start3 months lateforecast Feb 1, 2018
- Construction end5 months earlyforecast Mar 31, 2019
Also in Cape Breton
- Cape Breton Regional Municipality - Wastewater Treatment Infrastructure$39.2M
- Cape Breton University - Centre for Discovery and Innovation$20.0M
- Eskasoni First Nation Long Term Care Kiknu$19.7M
- Sydney Harbour West Wastewater Collection and Treatment$19.3M
- CBRM - Battery Electric Bus Purchase and Storage and Maintenance Facility - Phase 2$16.7M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47216 in the federal list. How to read these figures.