Fall River water servicing
Federal contribution
$3.4M
$3,403,739
Federal share43%
of $7.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 16, 2016
201720182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Regional Municipality of Halifax
- Construction start
- Sep 22, 2018(actual)
- Construction end
- Nov 28, 2018(actual)
Against the original forecast
- Construction start12 months lateforecast Sep 25, 2017
- Construction end4 months earlyforecast Mar 31, 2019
Also in Halifax
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47224 in the federal list. How to read these figures.